What is construction ITP?

An Inspection Test Plan ( ITP ) is a commonly required document often submitted with a construction quality control plan. This document details exactly what inspections and tests will be performed to control quality on your project.

What is ITP in quality management?

What is an Inspection and Test Plan? Also known as quality inspection plans, ITPs set out critical points at various stages within a process for scheduled inspections and verifications. This is to ensure the job is progressing as it should be, and that your quality assurance procedure is sound.

What are ITP documents?

The purpose of an Inspection and Test Plan is to put together in a single document that records all inspection and testing requirements relevant to a specific process. On a construction contract the process is likely to be a construction activity, element of work, trade work or providing a product section.

What is ITP in civil engineering?

An Inspection & Test Plan is the program of inspection, testing of materials, and survey shall be prepared and submitted by the contractor to the Engineer for approval before usage and application.With an inspection and test plan, you plan inspections and tests to catch defects or non conformance before they become

You might be interested:  Question: What Is Site Preparation In Building Construction?

What is difference between ITP and QAP?

QAP says “who will do, what will be done by whom etc” mainly designation and job responsibilities. ITP says “how much to be done, when to be done, what record to be made etc” mainly work related activities, their controlling documents and inspection frequencies.

How do I prepare for ITP?

Below we explore seven best practices to ensure your ITP works for you.

  1. Use an ITP Form.
  2. List Your Task Inspections.
  3. Add Your Milestone Inspections.
  4. Include Reference Documents.
  5. Make a Note of Responsibilities.
  6. Invite the Client to Witness the ITP.
  7. Display Times and Dates of Inspections.

What is the difference between ITP and ITR?

A good ITP will capture all inspection and test records and requirements into one site-specific document. A task specific Inspection and Test Record ( ITR ) will document each task in detail, including hold/witness points, test equipment, related documents, baseline data and known issues or defects.

What is an ITP diagnosis?

Idiopathic thrombocytopenic purpura is a blood disorder characterized by an abnormal decrease in the number of platelets in the blood. A decrease in platelets can result in easy bruising, bleeding gums, and internal bleeding. ITP may be acute and resolve in less than 6 months, or chronic and last longer than 6 months.

What is ITP test?

Diagnostic Procedures for ITP Includes a special blood test called an “anti-platelet antibody test.” Careful review of medications. Bone marrow aspiration: This test examines the platelet production and can rule out any abnormal cells the marrow may be producing that could lower platelet counts.

You might be interested:  Often asked: What Is A Lintel In Construction?

What is ITP in piping?

This content provides you with a draft Pipe Inspection and Test plan. This pipe ITP is general. If you have bought a manufactured pipes so witnessing of some tests is not possible and you can only review the manufacturer test reports.

What is QA QC inspection?

Quality ASSURANCE & Quality control. Quality Glossary Definition: Quality assurance / quality control ( QA / QC ) Quality assurance ( QA ) and quality control ( QC ) are two terms that are often used interchangeably.

What is the meaning of hold point in ITP?

A Hold Point is a mandatory verification point beyond which work cannot proceed without approval by the designated authority, typically the Engineer or Consultant or 3rd Party Inspector.

What is QAP?

A Quality Assurance Plan ( QAP ) is used to define the criteria and processes that will ensure and verify that data meet specific data-quality objectives throughout the Data Lifecycle.