What does practical completion mean in building?

Practical completion is when a project is ‘practically complete’, in the sense of the works being capable of being used, as distinct from when they are completely finished (with all defects rectified).

What is the difference between practical completion and final completion?

Practical completion is the date nominated in the contract for the works to be substantially completed and available for use. This may be subject to change. At the satisfactory completion of any required rectification work, your architect will issue the final certificate.

How long does it take to go from practical completion to handover?

So from practical completion to handover, it’s generally about a two-week mark. So handover is when we give you the keys to the house, and when the house has had its final clean, ready to go.

What do you check at practical completion?

What is inspected for at Practical Completion / Handover:

  • Building defects.
  • Damage.
  • Cosmetic defects.
  • Quality of finish.
  • Fixtures and fittings.
  • Presence of appliances.
  • Presence of installations.
  • Incomplete work.
You might be interested:  Readers ask: What Is A Construction Hazard?

What is needed for practical completion?

To achieve Practical Completion, the Contractor must comply with clause 2.37 (JCT Design and Build) and provide the Employer with contractor’s design documents and any related information specified in the Contract that show or describe the work (i.e. As Built Drawings, O & M Manuals which show the operation and

How long is practical completion stage?

Practical completion stage: 7-8 weeks.

Who signs off practical completion?

The contract administrator certifies practical completion when all the works described in the contract have been carried out. Certifying practical completion has the effect of: Releasing half of the retention (an amount retained from payments due to the contractor to ensure they complete the works).

What happens after practical completion inspection?

Following inspection of the items at PCI 2, the home is ready for handover and sign off can take place at the builder’s head office. Prior to picking up your new home keys, please ensure that you have arranged home insurance as the builder’s insurance is no longer active.

What is final completion?

Final Completion means the date determined and certified by A/E and Owner on which the Work is fully and satisfactorily complete in accordance with the Contract.

What happens on handover day?

On handover day you’ll receive: your occupancy permit or the equivalent certificate from a building surveyor, warranty and instruction documentation for appliances and fixtures, and. any other documentation from service providers (e.g. for supply of electricity, water, sewerage, gas etc.)

What happens practical completion?

There is no standard definition of practical completion. Generally, it is the point at which a building project is complete, except for minor defects that can be put right without undue interference or disturbance to an occupier.

You might be interested:  What Fire Safety Equipment Is Required On A Construction Site?

What is date of practical completion?

Practical completion (PC) occurs on the date a certificate of PC is issued by the Superintendent, even if the certificate states that PC occurred on an earlier date, the contractor claims that PC was achieved earlier, and the Superintendent agrees that PC was achieved earlier.

What do practical completion inspections look for?

When You Need a Practical Completion Inspection The practical completion inspection is one of the most important inspections you’ll have performed on your new home. It’s a chance to identify all building defects and have them rectified by the builder before you finalise the handover.

What is involved in a final inspection?

During the final inspection the building inspector will inspect that the house is complete and that all life and safety items meet code. A final inspection will probably last about 1 hour. Prior to the final inspection the Builder should do a pre- inspection to ensure that it is ready for the Final.

What should I check during PCI?

Practical Completion Inspection – 12 Hints

  1. Take your time.
  2. Look at things from a different angle.
  3. Take your shoes off and walk round in stocking feet then you can feel any problems with the floor.
  4. Turn on the Taps.
  5. Run the showers and check they drain.
  6. Flush the toilets, check they are securely fixed to floor and don’t leak.